The U.S. Army Corps of Engineers Louisville District will host a public meeting to discuss the dam remediation project on the Rough River Lake Dam.
The meeting will include the Rough River Dam Remediation project status and a briefing on the remediation process. The next phase, which was scheduled to be advertised in December 2017, has been postponed pending the review and
analysis of the project design to better address the project risk and increase the long-term effectiveness.
The 2019 early draw down to facilitate construction will not occur, and the likelihood of it being necessary is now significantly less. The upcoming phases of work will be discussed by dam safety experts and include cost and schedule.
The public meeting will be held from 6 until 8 pm CST on March 5 at the Rough River State Park Lodge in Falls of Rough.